A written answer, marked

A question from an ARE mock paper, answered and marked. From How to Prepare for the ARE 5.0: A Practical Guide.

Paper — Rooftop equipment change — exhibit-based decisions09:16
78%Rooftop equipment change — exhibit-based decisions — marked7/9 marks · 09:16 taken

The equipment schedule shows a 600 lb rooftop unit. The contractor submits an 850 lb unit and asks the architect to approve it. The structural exhibit provides no capacity for the proposed unit. Based on the supplied contract excerpt, identify the immediate response and the information or workflow needed before the change can proceed.

7/9

I would not approve the unit as submitted. The proposed equipment is 250 lb heavier than the scheduled unit and the structural exhibit does not establish capacity. I would request structural review and the equipment data. The architect should review the submittal for conformance, while the contractor remains responsible for means and methods. A change in scope or price must follow the contract process.

The answer uses the relevant schedule and structural exhibit, identifies the unverified load and distinguishes the architect’s review from the contractor’s responsibility. It also recognises that a scope or price change needs the contract process.

Missed

State that the discrepancy and pending information should be documented and routed to the parties authorised by this project’s contract before treating the change as accepted.

Model answerDo not approve the proposed unit as submitted: the schedule identifies a 600 lb unit, while the submittal is 850 lb, and the structural exhibit gives no capacity for that proposed load. Request the equipment data and structural review needed to assess the loading and support conditions. Under the supplied excerpt, the architect reviews for conformance with the contract documents; the contractor retains responsibility for means and methods. Record the discrepancy and the information requested. If the proposal changes scope or price, use the contract’s stated change process and route the decision to the authorised parties.

A practice case answer is assessed for exhibit use, technical reasoning, contract roles and a documented next step.
Start studying for ARE

Yours are written from your own notes, and the free plan needs no payment details.

Guides

Preparing for ARE? Build your ARE board from your own notes — the cards, papers and lectures are written from it. Free plan: 20 cards, a paper, a lecture and a viva to try.

Start on MySummaries

Other exams