Exam preparation
ARE
- Multiple choice
- Case-based
- United States
- Architecture
- National Council of Architectural Registration Boards
4 guides for this exam — how to prepare, what to practise, and how to know it has gone in.
Plan your ARE revision: a day-by-day calendar up to your exam date, free and without an account.
A written answer, marked
A question from an ARE mock paper, answered and marked. From How to Prepare for the ARE 5.0: A Practical Guide.
The equipment schedule shows a 600 lb rooftop unit. The contractor submits an 850 lb unit and asks the architect to approve it. The structural exhibit provides no capacity for the proposed unit. Based on the supplied contract excerpt, identify the immediate response and the information or workflow needed before the change can proceed.
7/9I would not approve the unit as submitted. The proposed equipment is 250 lb heavier than the scheduled unit and the structural exhibit does not establish capacity. I would request structural review and the equipment data. The architect should review the submittal for conformance, while the contractor remains responsible for means and methods. A change in scope or price must follow the contract process.
The answer uses the relevant schedule and structural exhibit, identifies the unverified load and distinguishes the architect’s review from the contractor’s responsibility. It also recognises that a scope or price change needs the contract process.
Missed
−State that the discrepancy and pending information should be documented and routed to the parties authorised by this project’s contract before treating the change as accepted.
Model answerDo not approve the proposed unit as submitted: the schedule identifies a 600 lb unit, while the submittal is 850 lb, and the structural exhibit gives no capacity for that proposed load. Request the equipment data and structural review needed to assess the loading and support conditions. Under the supplied excerpt, the architect reviews for conformance with the contract documents; the contractor retains responsibility for means and methods. Record the discrepancy and the information requested. If the proposal changes scope or price, use the contract’s stated change process and route the decision to the authorised parties.
Yours are written from your own notes, and the free plan needs no payment details.
Guides
- How to Prepare for the ARE 5.0: A Practical GuideA practical ARE 5.0 preparation method for selected-response questions and exhibit-based case studies, with a repeatable way to review mistakes.
- ARE Study Plan: A Week-by-Week Guide for CandidatesBuild an ARE study plan around focused sessions, case-study exhibits, code reasoning and regular review, with a practical eight-week schedule.
- ARE Flashcards for ARE 5.0: A Practical Study DeckStudy 18 ARE 5.0 flashcards on case-study exhibits, code decisions, contracts and construction administration, with a method for reviewing them.
- ARE Practice Questions: 10 Case-Study ScenariosWork through 10 original ARE practice questions on exhibits, code logic, contracts, coordination and professional judgement.
Preparing for ARE? Build your ARE board from your own notes — the cards, papers and lectures are written from it. Free plan: 20 cards, a paper, a lecture and a viva to try.
Start on MySummaries